Hyderabad is taking steps to strengthen its drinking water supply as the city prepares for higher demand in the coming months. The Hyderabad Metropolitan Water Supply and Sewerage Board (HMWSSB) is working to bring an additional source of water to the city.
The pipeline connection between Mallannasagar and Ghanpur Master Balancing Reservoir has reached its final stage. Officials are aiming to complete the remaining work within two days and conduct a trial run immediately afterwards.
The project involves connecting a 1,600-mm pipeline to transfer Godavari water to Hyderabad. The work faced delays due to hard rock along a 150-metre stretch in a forest area. However, the pipeline junction work at Ghanpur has been completed.
Through this project, the Water Board aims to bring an additional 40 million gallons per day (MGD) of Godavari water to the city. This supply is expected to meet nearly half the shortfall in areas that depend on the Singur-Manjeera sources.